St. Croix River walleye
Fishing Information About the St. Croix River  
About the St. Croix River
Public Access to the St. Croix River
Fish Species of the St. Croix River
Fishing Photos  
Forum  
Videos  
Fishing Guide on the Saint Croix River
Asian Carp Updates Relating to the St. Croix River
St. Croix River Crossing Near Stillwater, MN
Cities on the River  
Related Links  
 
Top 10 Reasons to Fish the St. Croix River
       
  St. Croix River Fishing Good fishing... beautiful scenery... historic river towns. We’ll hook you up.
No Wake - New Bridge Near Stillwater, MN
No Wake Schematic
For the safety of workers and stability of equipment, boaters are required to slow down through a one-mile portion of the river near Bayport, MN.
Construction Updates
by MN DOT
MN DOT
Construction WebCam
by MN DOT
webcam

Aerial View
Project Visualization
(No Audio)
Run Time: 1:20

You Tube

St. Croix River Crossing
Project Visualization
with Voiceover
Run Time: 14:46

You Tube

Loop Trail
Project Visualization
with Voiceover
Run Time: 9:40

You Tube

Bridge Design
Attempts to Minimize Environmental Impact
Run Time: 5:46

You Tube
Load Testing
Began in June, 2012
Run Time: 2:15
You Tube
Project Layout
Aerial View
PDF
Shoddy Mill
Historical Buildings
Moving to Stillwater
Run Time: 3:31
Shoddy Mill and Warehouse
Coalition for
the St. Croix
River Crossing

Coalition
 
Related Links
April 23, 2014 - Paddleboat Tours of Bridge Construction
May 30, 2013 - Breaking Ground for the St. Croix River Crossing
May 26, 2013 - No Wake Zone on St. Croix for Bridge Project
May 15, 2013 - St. Croix RIver Bridge Open Houses Slated
March 15, 2013 - Wisconsin to Begin St. Croix River Bridge Land Purchases
February 19, 2013 - Tolls on the St. Croix River Crossing?
February 6, 2013 - Road Construction Begins in April
December 28, 2012 - Old Dream Becomes New Bridge
December 12, 2012 - St. Croix River Bridge Project May Result in Incidental Take of Rare Mussels
December 7, 2012 - Stillwater Lift Bridge Repoens Ahead of Schedule
November 7, 2012 - Ground Work Begins this Week
October 8, 2012 - Pier Construction Begins in Late Spring, 2013
September 18, 2012 - Stillwater Patch Blog: St. Croix River Crossing
September 10, 2012 - Stillwater Lift Bridge Closed for Repairs Until December, 2012
August 23, 2012 - St. Croix Bridge Clears Its Final Hurdle
June 26, 2012 - Engineering Firm, HDR, Chosen to Lead Bridge Design
June 12, 2012 - Crews Begin Load Tests in St. Croix River This Month
April 28, 2012 - Muck Sucks Up Money for Bridge Project
April 12, 2012 - Lift Bridge Repairs Could Affect Endangered Mussels
March 14, 2012 - President Obama Signs Stillwater Bridge Bill
March 9, 2012 - Bridge Bill Awaits President Obama's SIgnature
March 3, 2012 - Supporters Celebrate Legislative Victory
May 11, 2011 - Stillwater River Crossing Brings Local Debate to National Stage
January 19, 2011 - New Stillwater Bridge Could Be a Toll Bridge
St. Croix River Crossing Project, Minnesota
US. Department of Transportation Federal Highway Administration
November 30, 2001 A Conflict Assessment of The Existing and Proposed St. Croix River Bridges
MN DOT Project Website Project Visualization
New River Bridge Near Stillwater, MN
Construction will take about three years to complete.
The new bridge is scheduled to be open for traffic in 2016.
St. Croix River CrossingProject visualizations by the Minnesopta Department of Transportation.
2013-2014 Stillwater Crossing 2013-2014 Stillwater Crossing
Road construction completed and planned for Oak Park Heights, MN (2013-2014). Click here for an enlarged view. Road construction phasing for 2014 (Oak Park Heights). Click here for an enlarged view.
 

St. Croix Crossing
The St. Croix Crossing
(project offices)
1862 Greeley Street South
Stillwater, MN 55082

Office hours are 8 a.m. - 4:30 p.m.
Monday - Friday.

 
Stay Connected... Be Informed
Sign-up for project email updates
Like the project Facebook page
Follow the project on Twitter
Visit the project website
Call project hotline at 1-855-GO-CROIX
(1-855-462-7649)
Email the project team at stcroixcrossing.dot@state.mn.us
 
Project Overview:
St. Croix River Crossing

St. Croix River bridge crossing location
The red dotted line marks the location of the new bridge and highway. Purple marks the existing Stillwater Lift Bridge.

Stillwater Lift Bridge
The existing Stillwater Lift Bridge

This major project will divert traffic from the 80-year-old Stillwater Lift Bridge to a four-lane bridge that will connect expressways on both sides of the St. Croix River. Currently, severe traffic congestion in downtown Stillwater causes pedestrian and traffic safety problems, which are amplified by Lift Bridge operations.

The St. Croix Crossing project will provide a safer, more reliable river crossing. The project includes a four-lane river bridge, new roadway approaches on both sides of the river, historic and environmental mitigation, and extensive trail facilities that will include converting the Lift Bridge to a bike and pedestrian facility. The project will provide jobs for suppliers, subcontractors, disadvantaged business enterprises as well as general contractors.

The existing St. Croix River crossing at Stillwater, Minnesota, is a highway bridge connecting downtown Stillwater to the Town of St. Joseph in St. Croix County, Wisconsin. The crossing consists of a 1,050‑foot-long, 10-span, 2-lane bridge and a 750-foot earthen causeway extending from the Wisconsin shoreline. It is known as "the Lift Bridge," because one of the spans is a distinctive vertical lift span.

The bridge, which opened in 1931, was listed on the National Register of Historic Places in 1989. Frequent raising of the bridge to allow boats to travel the St. Croix River causes traffic congestion in Stillwater and Houlton, Wisconsin, as traffic backs up to wait for the bridge to lower and resume vehicular traffic.
History of Debate
Consideration of a replacement bridge over the St. Croix River near Stillwater began in the early 1970s. Formal assessment of alternatives began with the preparation of the St. Croix River Crossing Draft Study Outline and Scoping Document (1985). Alternatives assessed with the 1985 document eventually led to the analysis of three river crossing corridor alternatives and two tunnel alternatives with the 1990 Draft Environmental Impact Statement (EIS). In 1995, the Final EIS identified a preferred alternative, and a Record of Decision was issued on July 10, 1995.
In April 1995, Mn/DOT, Wis/DOT, and FHWA completed a Final EIS and Section 4(f) Evaluation for a replacement bridge about 1,920 meters (6,300 feet) south of the existing Stillwater Lift Bridge. A Record of Decision (ROD) was issued by FHWA in July 1995, and work began on the final design of the river crossing and the approach roadways. Right-of-way was acquired, and site preparation work was initiated. In 1996, the National Park Service (NPS) evaluated the project under Section 7(a) of the Wild and Scenic Rivers Act and found that the project, as proposed, would have a direct and adverse effect on the outstandingly remarkable scenic and recreational values for which the Lower St. Croix River was included in the National Wild and Scenic River System. As a result of this finding, federal permits from the U.S. Army Corps of Engineers and the U.S. Coast Guard could not be issued for the project, and the project was not allowed to proceed. In April 1998, the U.S. District Court upheld the NPS determination.
In an effort to determine whether any crossing of the Lower St. Croix National Scenic Riverway was feasible near Stillwater, Mn/DOT and Wis/DOT invited Richard P. Braun, a retired Mn/DOT transportation commissioner, to perform an independent review of the project. Braun was asked to review the need for a replacement crossing and to investigate potential bridge alignment alternatives. In addition, he was asked to recommend an alignment and type of bridge structure that would be both feasible to construct and acceptable for implementation by the key interested parties. Between June and September of 1998, Braun conducted extensive discussions and meetings with many individuals and organizations, and facilitated public meetings with a 21-member advisory group (the St. Croix River Crossing Advisory Group) that included representatives from federal and state regulatory agencies, local and regional units of government, environmental groups, historic preservation groups, and chambers of commerce.
Braun recommended a four-lane, deck-tied, steel arch bridge on an alignment 1,100 meters (3,600 feet) south of the existing Stillwater Lift Bridge. The proposed bridge would cross the river perpendicularly and would be shorter than the 1995 Final EIS Preferred Alternative. The alignment would also take advantage of an existing ravine on the Wisconsin bluff, thereby reducing potential impacts on the Lower St. Croix Valley. A large majority of the St. Croix River Crossing Advisory Group agreed that they could accept the Braun recommendations.
 
St. Croix RIver Bridge span
Unlikely Allies Agree — the New St. Croix River Bridge Crossing is Needed
Minnesota Governor Mark Dayton and U.S. Representative Michelle Bachmann both agree on building a new bridge over the federally protected St Croix River. Bachmann worked closely with Wisconsin lawmakers to introduce legislation in Congress to create an exemption from the Wild and Scenic Rivers Act that allows a new four-lane St. Croix River bridge to be built in the near future.
Legislation proposed by Senators Klobuchar, Kohl, Franken, and Johnson was important milestone for Minnesota and Wisconsin in the process of addressing a transportation problem that has plagued the region for decades.
Community members and state and federal agencies worked together for years to develop the best solution to the problem. These stakeholders studied dozens of alternatives and answered questions about the need for a new bridge, the project costs, and the location of the bridge before determining that the St. Croix River Crossing is the best solution to the region's transportation issues.
The senators spent time reviewing the project, looking at the facts, and meeting with people on different sides of the issue. Their support for the plan is yet another validation that this is the best solution postiioned in the right location to handle these transportation needs, respect the region's history, and preserve an important natural resource.
 
Facebook Like Us!
Website by Saint Croix Creative, Inc.        Email: info@stcroixriverfishing.com